construction continues along. we now have 16 homes under construction. building 21 is on track to be finished by June 20 and building 1 is right behind, finishing up in July. we are presently installing cabinets and finishing up the stucco and painting in building 21 and the sheetrock is being completed in building 1. we have also started two new foundations – buildings 2 and 22. come check us out!